Pennsbury High School Project

This page contains updates on the proposed construction of a new Pennsbury High School.
Please check back frequently for updates.

 PUBLIC NOTICE   

PENNSBURY HIGH SCHOOL PROJECT 

CONTRACTOR QUALIFICATION FORM

Pennsbury School District is seeking to identify and engage as many qualified contractors as possible for the upcoming Pennsbury High School construction project. Bids are expected to be released shortly after the new year. 

This major project represents an exciting opportunity to partner with the district on the construction of a new high school that will have a positive impact on our entire community for decades to come. Interested contractors are encouraged to review our Responsible Contractor Policy and complete the linked Contractor Qualification Form by DECEMBER 5 to ensure they are eligible to participate in the competitive bidding process once it opens.

Click here to view the 2025-11-03 Pennsbury School District - RCP Advertisement R.1

Click here to view the Pennsbury School District Responsible Contractor Policy

Click the orange button or scan the QR Code to access the Contractor Qualification Form

Contractor Policy Button

Contractor QR Code

 

On June 15, 2023, the Pennsbury School District Board of Directors passed the 2023-24 school budget that includes a financial commitment for a major change to the Pennsbury High School campus (either a major renovation to the West campus or the construction of a new high school on the grounds of the current high school campus). This project will take several years to complete.

On November 9, 2023, the Pennsbury Facilities Committee approved the construction of a new high school. The Pennsbury Board of Directors approved the project at its monthly meeting on November 16, 2023. All PHS Project videos are available by clicking the link on the left-hand side of the page.

Now that the architect has been selected, the design process starts. Multiple meetings will be held for community members, students, and staff to provide input on the final design of the new Pennsbury High School. We are planning about twelve community design meetings covering various topics that will take place over the next six months. Dates and locations will be shared once they are confirmed. Please click on the "PHS Project Community Design Meetings" link on the left-hand side of the page for more detailed information. 

Tentative PHS Project Schedule

July - November 2023

  • Discussions/Assemble Committee
  • Community Meetings
  • Site Surveys, GeoTech Investigation, Hazardous Materials Investigation

November/December 2023

  • RFP for Architect and School Design

January 2024 -November 2025

  • Assemble Design Committee
  • School Visits
  • Community Presentations
  • Design and Construction Approvals
  • Act 34 Hearing (September 4, 2025)

December 2025 / January 2026

  • Bids Released
  • Bids Approved

Late Spring 2026

  • Construction Starts

Fall 2029

  • One New Building Opens